News from the Streets – May 2026

Romford Road

Moving west to east:

Sections B South (Radlett Close to Tavistock Road) and D South (Green Street to Woodgrange junction) have received their blue surfacing at crossovers:

There is good progress on Junction 3 (Richmond Road/Green Street), which will lead directly into Section D. There’s even now an information board on the hoardings telling you what the finished scheme will look like!

Kerblines for Section F (Balmoral Road to Station Road via Woodgrange Park station) continues to make progress steadily eastwards on the north side only at this stage.

Section H (Rabbits Road to Little Ilford Lane) is now lined and open for use in both directions, and has also received its blue surfacing at side roads. We are pleased to see this significant and challenging section opened, including Romford Road’s first inline ‘sparrow’ type crossing. This offers benefits for all users:

  • When you are crossing as a pedestrian, you deal with cyclists and drivers separately, making the task of crossing the street easier to manage.
  • If you’re cycling, you don’t need to stop when the general traffic light is red—you just give way to people using or waiting for the zebra crossing as normal.
  • Shorter crossing distance for pedestrians means the pedestrian traffic light phase can be shorter, meaning less red time for buses and cars.

There will be an opening event for this new section on 19th May featuring a Dr Bike mechanic. Come down and celebrate!

Section I (Little Ilford Lane to Lugg Approach) is still in progress, and as we understand is being bundled with the works for Junction 7 (Little Ilford Lane junction.) This will include 2 new parallel crossings and, most excitingly, a protected T-junction at Little Ilford Lane. When complete, these will mean a big chunk of the scheme is effectively complete from Rabbits Road all the way to Lugg Approach.

Looking ahead, we hope that work will also be able to start in the coming months on Woodgrange Junction (junction 2, again connecting to Section D) and that Rabbits Road junction (junction 7) can see get in the ground this year.

Finally, we are aware of the topic of vehicles being parked in the cycle track, both for loading (which they shouldn’t be doing) and antisocially. While things are improving, it’s still not uncommon to see people loading or even with their cars fully parked in the cycle track. Please report these issues to the Romford Road team using the email address STRomfordRoad@newham.gov.uk, it helps make the case for measures such as bollards and block boulders to keep the cycleways and footways clear.

Water Lane parallel crossing

Work has now moved to the Manbey Grove side of the crossing. The footway rebuild on the eastern side is complete, with only the cycle track due to receive its final surfacing (which we assume will happen at the same time as the new crossing is raised.)

We particularly like the multi-coloured block paving—a simple way to jazz up the built environment. This scheme will make a big difference to the Maryland Cycleway link.

Leyton Road / Cycle Future Route 7

The cycle track is still waiting for its top surface, but the kerb lines are now extant as far as the future Decapod Street/Henniker Road crossing, the realigned Cycleway 16 route. The lamp post has also been removed from the cycleway. We hope that there will be further progress on this route in the coming months—it would be nice for our next ride with Colegrave School to use the new protected cycleway all the way!

Unfinished two-way cycle track with a connection to a side street. Crossing of connection uses buff rectangular tactiles.
The future route of Cycleway 16 – getting closer. Photo: Jonathan Rothwell

Westfield Avenue

International Way and Olympic Park Avenue junctions are now both open for use. At time of writing, the Olympic Park Avenue cycleway received its markings in the last 72 hours—and the freshly-resurfaced bridge span is very smooth and a joy to cycle on (with the exception of short strips by the bridge’s expansion joints.) Work is still ongoing around the entrance to the construction site opposite Olympic Park Avenue—so be careful for the time being.

Work is now beginning in earnest on the new expanded footway on the last section to the Marshgate Lane junction—with a new footway on the eastern side of Westfield Avenue for the very first time.

The parallel crossing connecting to Anthems Way is also complete. There is still some outdated signage (including a battered and now incorrect ‘no cycling’ sign) to be removed.

Elsewhere in the Olympic Park

The main structure of the expanded Greenway ramp to Marshgate Lane is now visible, although there is still clearly a way to go until it gets its tarmac surfacing and the surrounding landscaping is complete. The end date of “Spring 2026” (already extended from Autumn 2025) seems very optimistic. Hint: if you’re in the area, be prepared to give visitors in sparkly garb directions to the ABBA Arena.

The (somewhat stop-start) cycle track on Pool Street is largely complete, and is being connected to the extended Carpenters Road cycleway at one end, and Montfichet Road’s legacy cycle track on the other end.

Beckton Corridor

The section of Jake Russell Walk (National Cycle Network 13) between Royal Albert Way bridge and Beckton Park has been resurfaced, to the same standard as the rest of the Beckton Corridor—the awful anti-cycling barriers are gone, and the surface is smooth asphalt. Some finishing work is still being done to the footway at the crossing to Beckton Park, which we feel should really be a parallel pedestrian and cycle crossing.

Royal Docks Corridor—City Hall area

The extended section of the Royal Docks scheme along Western Gateway to the bike bus stop continues. The rain gardens for the medians are now almost fully planted, and the north-side cycle track connecting to the bike bus is awaiting its top surfacing and its connection to the existing cycle track on Tidal Basin Roundabout. The footway is in the process of being reconstructed. The cycle track on the City Hall/Kamal Chunchie Way/cable car side is still to be constructed.

News from the Streets — February 2026

Romford Road

Sections B and D westbound are largely complete and have been open since just before Christmas. Greenery is still to arrive in some of the rain gardens. We are also still waiting for the blue surfacing at the crossovers on these sections, which can only be done after a period of dry weather. The cycle tracks are already being well used and work well at rush hour—and traffic flows well, even bounded on both sides by the Earlham LTN and the newly-permanent West Ham Park LTN. So this is something great to celebrate!

Sections H is largely complete, but will not be opened until the junctions receive their blue surfacing. We also believe that section I is being held up by a serious flooding issue that Thames Water are taking a long time to resolve. We hope that once they are formally opened, the serious issues with people parking their cars on the cycle track outside the shops can be resolved.

Work on Green Street/Richmond Road junction is underway. The “classic” road closure that was at the roundabout with Windsor Road has now been relocated, and work is moving to the area of the junction itself. This will provide a new, protected cycleway for the east-west alignment, and toucan crossings to permit cycling movements to Green Street, along with rain gardens and resurfacing.

Work has also begun on Section F, with kerb lines starting to appear for the new cycle track eastbound from Balmoral/Katharine Road junction.

Finally, we understand that once work completes on Green Street junction—hopefully in summer—work should begin on Woodgrange junction, assuming no further delays in traffic modelling. We certainly hope that Thames Water’s existing works at this junction do not overrun or cause further issues.

Water Lane crossing

Work has, at long last, begun on the priority pedestrian and cycle crossing of Water Lane on the Stratford-Forest Gate backstreet Cycleway link, with its unusual diagonal design. This will also add a zebra crossing closer to the junction with Forest Lane, which is desperately needed by users of Maryland Station. It will also introduce new mode filters at the Manbey Grove and Louise Road junctions, further strengthening the successful Manbey and Atherton LTNs. We hope that the speed humps will also finally do something to control the serious issue with traffic speed on Water Lane.

Westfield Avenue

The new cycle track, which was consulted on back in 2022, is now open all the way from Montfichet Road to Olympic Park Avenue, with work ongoing on the International Way and Olympic Park Avenue junctions—the latter of which has now closed off the rat-run from Westfield car parks through East Village, for conversion to a protected cycle track. Planting has started to arrive in the rain gardens. We expect that once the junctions have finished, the last section of cycle track (and new pavement) will be built to connect to Marshgate Lane junction.

The cycle track is already proving popular, and not just with people cycling—we’re glad that Stratford’s rollerbladers finally have somewhere around Westfield they can feel welcome!

Leyton Road / Cycle Future Route 7

The permanent traffic lights are finally turned on at Chobham Road/Leyton Road/Liberty Bridge Road junction, albeit with the cycle crossings currently closed as the tracks have yet to receive their top surfacing. The cycle track is starting to creep its way southwards. The current phase of works, we believe, will run as far as Windmill Lane junction, as the extension over the Angel Lane bridge to join Great Eastern Road is dependent on a development in the area.

We understand design work is being sped up where possible on the southern section of CFR7, from Stratford to Plaistow, in reaction to the Greenway closure, and hope to learn more about this soon.

Royal Docks

The entirety of the Royal Docks corridor’s 5-stage initial scope is now complete, and an additional phase—funded by the original corridor coming in under budget and some extra external funding—is now underway to extend it to Seagull Lane (for Royal Victoria DLR and the Silvertown bike bus stop) and the new City Hall. This will extend the cycleway, remove the dual carriageway, and remove all the traffic lights and replace them with priority crossings. This will make life easier and more convenient for pedestrians, cyclists, and for the few drivers who use this street. Extra rain gardens will also appear which should make this somewhat windswept area much more attractive.

Map of a layout for Western Gateway and Tidal Basin Road east of Tidal Basin Roundabout, with 2-way cycle tracks on the northern and southern sides and parallel pedestrian/cycling crossings over Western Gateway.
Image: Newham Council

Good progress has been made since work started in October and the first section of new cycle track is already being used (albeit as a temporary footway while the main footway is being rebuilt.) We look forward to revisiting our City Hall to City Hall video once the works are done!

Additional projects

  • Progress is being made on the cycleway at Pool Street by the London Aquatics Centre, which will include a short section of separated cycle track (albeit disappearing regularly into shared areas.) We are pleased that this will considerably reduce the carriageway to a sensible width, and believe this will eventually link to a protected track on Carpenters Road (both the existing one and an extension as far as Sidings Street.)
  • The new ramp up to the north end of the Greenway at Marshgate Lane is still in progress. We understand that improved art and wayfinding for the underpass, which should make it much less grim, should be finished by the summer (hopefully with the new ramp.)
  • The West Ham Park LTN has been made permanent. We note that in the Cabinet meeting where the approval was voted through, the Mayor of Newham read out a letter from the head teacher of Park Primary School in support of the LTN. We feel that this, plus powerful messages from residents with their personal experiences of cleaner air and safer streets, helped the Cabinet and councillors to make the right decision—and will hopefully make it much harder for anyone hoping to take the LTN out in future.
  • The Beckton Corridor has been resurfaced, and the cycle tracks and crossings around ASDA are finished. Jake Russell Walk, which previously had an appalling tiled surface, is currently being resurfaced as well—this will connect the new Beckton Corridor and (hopefully) new cycle tracks on Woolwich Manor Way to the Royal Docks.